SIA Felts Field Airport Electrical Improvements – Spokane, WA

Overview

The Airport determined that the majority of the existing airfield circuits were past their useful life and did not meet standards for airfield electrical systems. As the prime consultant, J-U-B’s Electrical Engineering Group conducted detailed site investigations prior to preparing detailed construction documents to upgrade all airfield lighting and control systems. A project phasing plan was completed in coordination with airport management and users. Full bid and construction services were provided including a full-time resident engineer to observe and manage the construction phase of the project.

The project included:

  • Airport lighting system as-built research and documentation
  • Construction phasing plan
  • New 3L/21R runway lighting
  • New threshold lights
  • New taxiway lights for taxiways A, B, C, D and E
  • Replaced direct bury electrical cables with new conduit and wire
  • New electrical vaults
  • Pilot activated airport lighting control system (PAALC)
  • FAA construction and closeout documentation
  • Full time construction observation – Resident Engineer